Segment I-1 the crews recently placed concrete beams on the bridge that will travel over FM 1413 in Dayton, TX. Bridge crossings within segment I-1 will become more visible to the general public in 2020. The construction of frontage roads, main lanes, and drainage infrastructure will continue.
Segment I-2, Over 80% of the Cedar Bayou lift bridge has been removed. Crews anticipate work to resume through January 2020 (photo) In 2020, GPI will focus its efforts on crossing SH-99 over IH-10 Frontage road ramps are currently being constructed Crews continue to work on main lanes, frontage roads, & drainage.