Final design and construction administration services for utilities to serve the Baytown Hotel and Convention Center Project

The City Council authorized the agreement for Professional Engineering Services with Kimley-Horn and Associates, Inc., in an amount not to exceed $122,400 for final design and construction administration services for utilities to serve the Baytown Hotel and Convention Center Project.

The future development of the Bayland Island Hotel and Convention Center requires the upsizing and relocation of existing utilities to meet future demands and capacity.  


In November 2019, the City entered into an agreement for Preliminary Design Engineering services with Kimley-Horn and Associates, Inc., in the amount of $48,900.00 with a Preliminary Engineering Report as the final deliverable.  

That work effort determined that the new development and future expansion of that development would require the relocation and upsizing of a sanitary sewer lift station and related sanitary sewer gravity and forcemain to serve the development.

This proposed work effort will complete the design of the sanitary sewer lift station, including layout, pump sizing, wet well structural design, electrical design, and screening. The lift station will be designed to meet floodplain requirements and power redundancy. This design will then be provided to the Hotel and Convention Center contractor to construct, via future agreement. The source of funds will come out of the MDD for 







the fiscal Year 2020. 